WEKO3
アイテム
Preparation of the cryomodule assembly for the Linear IFMIF Prototype Accelerator (LIPAc) in Rokkasho
https://repo.qst.go.jp/records/78371
https://repo.qst.go.jp/records/783716c9843ef-93c8-4996-a03f-6a4fcc90a7e1
Item type | 会議発表用資料 / Presentation(1) | |||||
---|---|---|---|---|---|---|
公開日 | 2020-01-08 | |||||
タイトル | ||||||
タイトル | Preparation of the cryomodule assembly for the Linear IFMIF Prototype Accelerator (LIPAc) in Rokkasho | |||||
言語 | ||||||
言語 | eng | |||||
資源タイプ | ||||||
資源タイプ識別子 | http://purl.org/coar/resource_type/c_c94f | |||||
資源タイプ | conference object | |||||
アクセス権 | ||||||
アクセス権 | metadata only access | |||||
アクセス権URI | http://purl.org/coar/access_right/c_14cb | |||||
著者 |
Ebisawa, Takashi
× Ebisawa, Takashi× Maebara, Sunao× Kondo, Keitaro× Kasugai, Atsushi× Sakamoto, Keishi× Bazin, Nicolas× Berry, Stephane× Dztiko, Herve× Phillips, Guy× Cara, Philippe× Ebisawa, Takashi× Maebara, Sunao× Kondo, Keitaro× Kasugai, Atsushi× Sakamoto, Keishi |
|||||
抄録 | ||||||
内容記述タイプ | Abstract | |||||
内容記述 | The commissioning of LIPAc (Linear IFMIF Prototype Accelerator) is ongoing at Rokkasho Fusion Institute of QST, Japan for the engineering validation of the low energy section of the accelerator up to 9 MeV. Several SRF cCryomodules are planned to be adopted in will be required for IFMIF at the downstream to accelerate deuterons from 5 MeV to 40 MeV, and . The first of these a cCryomodules will is currently being manufactured and will be installed and tested in on the LIPAc. This majority of the cryomodule Cryomodule, including the consists of 8 HWRs and RF couplers required for accelerating the beam, working at 4.45 K with 175 MHz RF and 8 RF couplers has been supplied by CEA. The and 8 superconducting solenoid magnet packages required for steering the beam will bes supplied by CIEMAT. The assembly of the cryomodule is will be completed under the responsible responsibility for of Fusion for Energy, with assembly work and has been carried out recently starting in at the QST Rokkasho site since in March 2019. In the initial plan of the project, the cryomodule was to be assembled in EU and transported to Japan. However, due to the design modification of the mechanical tuner, it was decided to perform the assembly in Japan in order to avoid a risk of damage by transportation after the assembly. Since there was no any working environment for such an assembly work in Rokkasho, Due to the cleanliness requirements for the assembly, QST took the responsibility to prepare the infrastructure of the an ISO 14644-1 class 5 cleanroom environment required for the cryomodule assembly from the scratch. A class 5 (ISO14644-1) clean room as well as some In addition, dedicated apparatus, e.g. a dedicated slow pumping system and other ancillary equipment, was prepared for the assembly. All equipment is now in operation having been installed and commissioned during 2018 and the early part of 2019. in Rokkasho so as to satisfy the requirement to provide the minimum cleaning equipment and working space just for the assembly of a cryomodule. In the present paper, the details of the preparation work for the cryomodule assembly made by QST will be presented. |
|||||
会議概要(会議名, 開催地, 会期, 主催者等) | ||||||
内容記述タイプ | Other | |||||
内容記述 | 19th International Conference on RF superconductivity | |||||
発表年月日 | ||||||
日付 | 2019-07-02 | |||||
日付タイプ | Issued |