Linear IFMIF Prototype Accelerator (LIPAc): Installation activities for Phase-B beam commissioning in Rokkasho
https://repo.qst.go.jp/records/49380
https://repo.qst.go.jp/records/49380161bf2e6-5aff-48d6-90a7-df66e9253dea
Item type | 学術雑誌論文 / Journal Article(1) | |||||
---|---|---|---|---|---|---|
公開日 | 2018-12-28 | |||||
タイトル | ||||||
タイトル | Linear IFMIF Prototype Accelerator (LIPAc): Installation activities for Phase-B beam commissioning in Rokkasho | |||||
言語 | ||||||
言語 | eng | |||||
資源タイプ | ||||||
資源タイプ識別子 | http://purl.org/coar/resource_type/c_6501 | |||||
資源タイプ | journal article | |||||
アクセス権 | ||||||
アクセス権 | metadata only access | |||||
アクセス権URI | http://purl.org/coar/access_right/c_14cb | |||||
著者 |
近藤, 恵太郎
× 近藤, 恵太郎× Marcos, Ayala Juan× Bolzon, Benoit× Cara, Philippe× Dzitko, Hervé× 蛯沢, 貴× Fagotti, Enrico× Gex, Dominique× Heidinger, Roland× 平田, 洋介× 一宮, 亮× 池田, 幸治× Jimenez, David× Jokinen, Antti× 春日井, 敦× 菊地, 孝行× Knaster, Juan× 小又, 将夫× 前原, 直× Marqueta, Alvaro× Moya, Ivan× 西村, 忍× 大平, 茂× 奥村, 義和× Perez, Mario× Phillips, Guy× IvanPodadera× GiuseppePruneri× 坂本, 慶司× Scantamburlo, Francesco× 新屋, 貴浩× 杉本, 昌義× Weber, Moises× 近藤 恵太郎× 蛯沢 貴× 平田 洋介× 一宮 亮× 池田 幸治× 春日井 敦× 菊地 孝行× 小又 将夫× 前原 直× 西村 忍× 大平 茂× 奥村 義和× 坂本 慶司× 新屋 貴浩× 杉本 昌義 |
|||||
抄録 | ||||||
内容記述タイプ | Abstract | |||||
内容記述 | The construction of the Linear IFMIF Prototype Accelerator (LIPAc) is in progress in order to demonstrate the feasibility of the low energy section of an IFMIF deuteron accelerator up to 9 MeV with a beam current of 125 mA in CW. The next milestone of the project is the so-called Phase-B beam commissioning, and one of the missions is to demonstrate the acceleration of the proton beam up to 2.5 MeV or the deuteron beam up to 5.0 MeV in pulsed mode with a low duty cycle of 0.1% through RFQ. Most of the components and subsystems necessary for Phase-B were delivered by 2016 under the responsibility of Fusion for Energy (F4E) as in-kind contributions of several European institutes, namely CEA (France), CIEMAT (Spain), INFN (Italy), and SCK-CEN (Belgium), and QST is in charge of the installation of the delivered equipment. The installation and check-out of the RFQ subsystem and the RF power system was completed by July 2017, and the RF conditioning of the RFQ cavity started. Also, the installation and the check-out of the important sub-systems for Phase-B, namely MEBT and beam diagnostics, have been completed. | |||||
書誌情報 |
Nuclear Materials and Energy 巻 15, p. 195-202, 発行日 2018-05 |
|||||
出版者 | ||||||
出版者 | Elsevier Ltd. | |||||
ISSN | ||||||
収録物識別子タイプ | ISSN | |||||
収録物識別子 | 2352-1791 | |||||
DOI | ||||||
識別子タイプ | DOI | |||||
関連識別子 | 10.1016/j.nme.2018.04.011 | |||||
関連サイト | ||||||
識別子タイプ | DOI | |||||
関連識別子 | https://doi.org/10.1016/j.nme.2018.04.011 | |||||
関連名称 | https://doi.org/10.1016/j.nme.2018.04.011 |