WEKO3
アイテム
IFMIF原型加速器(LIPAc)の高デューティビーム試験結果
https://repo.qst.go.jp/records/2004866
https://repo.qst.go.jp/records/200486697399fff-ec5f-4208-b5bc-81e6cc965d5e
| アイテムタイプ | 会議発表論文 / Conference Paper(1) | |||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 公開日 | 2024-12-27 | |||||||||||||||||||||||||||||||||||
| タイトル | ||||||||||||||||||||||||||||||||||||
| タイトル | IFMIF原型加速器(LIPAc)の高デューティビーム試験結果 | |||||||||||||||||||||||||||||||||||
| 言語 | ja | |||||||||||||||||||||||||||||||||||
| 言語 | ||||||||||||||||||||||||||||||||||||
| 言語 | jpn | |||||||||||||||||||||||||||||||||||
| 資源タイプ | ||||||||||||||||||||||||||||||||||||
| 資源タイプ識別子 | http://purl.org/coar/resource_type/c_5794 | |||||||||||||||||||||||||||||||||||
| 資源タイプ | conference paper | |||||||||||||||||||||||||||||||||||
| アクセス権 | ||||||||||||||||||||||||||||||||||||
| アクセス権 | metadata only access | |||||||||||||||||||||||||||||||||||
| アクセス権URI | http://purl.org/coar/access_right/c_14cb | |||||||||||||||||||||||||||||||||||
| 著者 |
赤木 智哉
× 赤木 智哉
× 長谷川 和男
× 近藤 恵太郎
× 熊谷 公紀
× 増田 開
× 杉本 昌義
× Benedetti Florian
× Carin Yann
× Chambrillon Janic
× Cismondi Fabio
× Dzitko Herve
× Gex Dominique
× Jimenez Rey David
× Moya Ivan
× Scantamburlo Francesco
|
|||||||||||||||||||||||||||||||||||
| 抄録 | ||||||||||||||||||||||||||||||||||||
| 内容記述タイプ | Abstract | |||||||||||||||||||||||||||||||||||
| 内容記述 | The Linear IFMIF Prototype Accelerator (LIPAc) is being commissioned under the international collaboration between the EU and Japan. LIPAc aims to accelerate a deuteron beam of 125 mA to 9 MeV and operate in CW mode, and consists of an injector, an RFQ, a Superconducting RF linac (SRF), a beam transport line, and a beam dump. Until recently, the LIPAc beamline was in its final configuration except for the SRF, which was for a high-duty beam operation called Phase B+ commissioning. The main objective of this commissioning was to validate high duty cycle deuteron beam operation and characterization of the beam. Phase B+ was completed at the end of June 2024, with a beam current of about 119 mA and duty cycle of up to 8.75% have been achieved. After the completion of the Phase B+, the SRF will be delivered to the accelerator room and installed in the beamline. The results of Phase B+ are presented in this paper. | |||||||||||||||||||||||||||||||||||
| 書誌情報 |
Proceedings of the 21st Annual Meeting of Particle Accelerator Society of Japan p. 162-165, 発行日 2024-10 |
|||||||||||||||||||||||||||||||||||
| 関連サイト | ||||||||||||||||||||||||||||||||||||
| 識別子タイプ | URI | |||||||||||||||||||||||||||||||||||
| 関連識別子 | http://www.pasj.jp/web_publish/pasj2024/proceedings/PDF/FROT/FROT07.pdf | |||||||||||||||||||||||||||||||||||