Beam Commissioning of the IFMIF EVEDA Very High Power RFQ
https://repo.qst.go.jp/records/67097
https://repo.qst.go.jp/records/67097a91a771a-ce51-427d-9696-81fba4575dd1
Item type | 会議発表用資料 / Presentation(1) | |||||
---|---|---|---|---|---|---|
公開日 | 2019-01-18 | |||||
タイトル | ||||||
タイトル | Beam Commissioning of the IFMIF EVEDA Very High Power RFQ | |||||
言語 | ||||||
言語 | eng | |||||
資源タイプ | ||||||
資源タイプ識別子 | http://purl.org/coar/resource_type/c_c94f | |||||
資源タイプ | conference object | |||||
アクセス権 | ||||||
アクセス権 | metadata only access | |||||
アクセス権URI | http://purl.org/coar/access_right/c_14cb | |||||
著者 |
Fagotti, Enrico
× Fagotti, Enrico× Antoniazzi, Loris× Bellan, Luca× Bortolato, Damiano× Comunian, Michele× Facco, Alberto× Giacchini, Mauro× Grespan, Francesco× Montis, Maurizio× Palmieri, Antonio× Pisent, Andrea× Scantamburlo, Francesco× Bolzon, Benoit× Chauvin, Nicolas× Gobin, Raphael× Cara, Philippe× Dzitko, Herve× Gex, Dominique× Jokinen Antti× Phillips, Guy× Ebisawa, Takashi× Kasugai, Atsushi× Kondo, Keitaro× Sakamoto, Keishi× Shinya, Takahiro× Sugimoto, Masayoshi× Heidinger, Roland× Marqueta, Alvaro× Moya martinez Ivan× Mereu, Paolo× Pruneri, Giuseppe× Weber, Moises× Francesco Scantamburlo× Benoit Bolzon× カラ フィリップ× ヨキネン アンティ× 蛯沢 貴× 春日井 敦× 近藤 恵太郎× 坂本 慶司× 新屋 貴浩× 杉本 昌義× Alvaro Marqueta× イヴァン モヤ マルチネス× Giuseppe Pruneri |
|||||
抄録 | ||||||
内容記述タイプ | Abstract | |||||
内容記述 | IFMIF, the International Fusion Materials Irradiation Facility, is an accelerator-based neutron source that will use Li(d, xn) reactions to generate a flux of neutrons with a broad peak at 14 MeV equivalent to the conditions of the Deuterium-Tritium reactions in a fusion power plant. IFMIF is conceived for fusion materials testing. The IFMIF prototype linear accelerator (LIPAc) is jointly developed by Europe and Japan within the IFMIF EVEDA project: it is composed of an ion source, a LEBT, an RFQ, a MEBT and a SC linac, with a final energy of 9 MeV. The 4-vane Radio Frequency Quadrupole (RFQ), developed by INFN in Italy, will accelerate a 130 mA deuteron beam from 0.1 to 5 MeV in continuous wave, for a beam power of 650 kW. The 9.8 m long 175 MHz cavity is composed of 18 x 0.54 m long modules flanged together and aligned within 0.3 mm tolerance. The RFQ was completed, delivered and assembled at the Rokkasho site and is presently under extended RF tests. The second phase of beam commissioning (up to 2.5 MeV/u) was scheduled to start at the end of 2017. Several unexpected issues and incidents significantly delayed the original program, which is however proceeding step by step toward the full achievement of its goals. | |||||